The MicroLogic X control unit provides information to help with scheduling preventive maintenance operations.
It monitors maintenance programs performed and generates events to indicate that maintenance is due.
For more information about maintenance programs and maintenance frequency, refer to DOCA0099EN MasterPact MTZ - Circuit Breakers and Switch-Disconnectors - Maintenance Guide.
The MicroLogic X control unit generates events to inform the user that maintenance needs to be planned.
A maintenance schedule event is completed when the date of the maintenance program performed is declared by using EcoStruxure Power Commission.
The schedule for maintenance operations depends on:
oThe operating and environmental conditions of the MasterPact MTZ circuit breaker.
oThe criticality of the user application.
oThe date of the last maintenance program performed, and declared by using EcoStruxure Power Commission software.
Basic and standard end-user maintenance schedule events and Manufacturer maintenance schedule events are calculated:
oFor the first event:
oFrom the commissioning date of the circuit breaker, if this date is declared by using EcoStruxure Power Commission software.
oOtherwise from the assembly date of the circuit breaker.
oFor subsequent events, from the date of the previous maintenance program (Basic, Standard, or Manufacturer) performed, if the date is declared by using EcoStruxure Power Commission software.
NOTE: Subsequent Manufacturer maintenance schedule events are calculated from the previous Manufacturer maintenance program performed and declared by using EcoStruxure Power Commission software.
If the date of the maintenance program performed is not declared by using EcoStruxure Power Commission software, the MicroLogic X control unit continues to use the commissioning date or assembly date to calculate the maintenance schedule events.
The following table summarizes maintenance operations for the three preventive maintenance programs:
Maintenance program |
Maintenance description |
Performed by |
---|---|---|
Basic end-user maintenance |
Visual inspection and functional testing, replacement of inoperative accessories. |
oTrained and qualified end-user personnel oTrained and qualified maintenance services provider personnel oSchneider Electric field service representative |
Standard end-user maintenance |
Basic end-user maintenance, plus operational servicing and subassembly tests. |
oTrained and qualified maintenance services provider personnel oSchneider Electric field service representative |
Manufacturer maintenance |
Standard end-user maintenance, plus diagnostics and part replacements by Schneider Electric Services. |
Schneider Electric field service representative |
The maintenance frequency is determined from the following recorded parameters and declared settings.
The following parameters for environmental conditions are recorded by the MicroLogic X control unit:
oTemperature
oPercent load
oHarmonics
oRelative humidity
oVibration
The following settings for environmental conditions and user application criticality are declared by using EcoStruxure Power Commission software (password-protected).
Setting |
Value |
Factory setting |
|
---|---|---|---|
Environmental conditions |
Corrosive atmosphere |
o3C1 (Rural area) o3C2 (Urban area) o3C3 (Immediate vicinity of industrial pollution) o3C4 (Inside polluting industrial premises) |
3C2 |
Salt environment |
oNone (No salt mist) oModerate (Salt mist < 10 km (6.5 mi) from seaside) oSignificant (Salt mist < 1 km (0.65 mi) from seaside) |
None |
|
Dust |
oLow level oModerate level oHigh level |
Low level |
|
User application criticality
|
oLow oModerate oHigh |
Low |
Recording Data of Maintenance Programs Performed
NOTICE |
INCORRECT MAINTENANCE SCHEDULE |
The date of the maintenance program performed must be declared by using EcoStruxure Power Commission software. |
Failure to follow these instructions will result in invalid maintenance schedule. |
After performing a preventive maintenance program, maintenance personnel must declare the following data by using EcoStruxure Power Commission software:
oMaintenance program performed: Basic, Standard, Manufacturer
oDate of maintenance operation
oName of service provider
oName of maintenance personnel
Maintenance schedule data is as follows:
oData of the last maintenance program performed, if the data is declared by using EcoStruxure Power Commission software:
oProgram performed: Basic, Standard, or Manufacturer
oDate of maintenance operation
oName of service provider
oName of maintenance personnel
oData of the next maintenance program to be performed:
oProgram to be performed: Basic, Standard, or Manufacturer
oEither the number of months before the program is due or the number of months it is overdue
Maintenance schedule data is available as follows:
oOn the MicroLogic X display screen at: Home > Maintenance > Assistance > Maint.schedule
oWith EcoStruxure Power Commission software
oWith EcoStruxure Power Device app through Bluetooth or USB OTG connection
oOn a remote controller using the communication network
The maintenance schedule function generates the following events:
Code |
Event |
History |
Severity |
---|---|---|---|
0x1480 (5248) |
Schedule basic maintenance within one month |
Diagnostic |
Medium(1) |
0x1481 (5249) |
Schedule standard maintenance within one month |
Diagnostic |
Medium(2) |
0x1482 (5250) |
Schedule manufacturer maintenance within three months |
Diagnostic |
Medium(2) |
(1) Disabled by default. Customizable with EcoStruxure Power Commission software. (2) Enabled by default, with pop-up messages. |
Code |
Event |
Recommended actions |
---|---|---|
0x1480 (5248) |
Schedule basic maintenance within one month |
Plan to schedule the basic preventive maintenance program within one month. To plan, edit, report, and track maintenance intervention, you may use EcoStruxure Facility Expert app. |
0x1481 (5249) |
Schedule standard maintenance within one month |
Plan to schedule the standard preventive maintenance program within one month. To plan, edit, report, and track maintenance intervention, you may use EcoStruxure Facility Expert app. |
0x1482 (5250) |
Schedule manufacturer maintenance within three months |
Plan to schedule the manufacturer preventive maintenance program within three months. To plan, edit, report, and track maintenance intervention, you may use EcoStruxure Facility Expert app. |
For information about the preventive maintenance programs, refer to DOCA0099EN MasterPact MTZ - Circuit Breakers and Switch-Disconnectors - Maintenance Guide.
Contact your field service representative for more information about who can carry out the recommended actions.