Prerequisites
The following is required to set up the Thermal Monitoring of MV Substations application in PME:
- PME 2023 must be installed and commissioned.
- The TH110 and CL110 sensors, the ZBRN32 access points, and the SMDs in the substation must be configured, connected, and communicating.
NOTE: This application supports SMD v4.0 and v3.0. SMD v2.0 is not supported.
- The SMDs must be accessible from the PME server by Ethernet.
- You must know the IP address of the SMDs.
NOTE: Each SMD needs a mid-range device license in PME.