Step |
Action |
---|---|
1 |
Verify the installation. For more information, refer to Verifying the Installation. |
2 |
Verify that a hazard and risk analysis has been performed. Refer to Hazard and Risk Analysis. |
3 |
Carry out a functional test of the Safe Force Off (SFO) function for all segments that need the safety-related function. |
4 |
Especially verify the correct application of the segments without the Safe Force Off (SFO) function. |
5 |
Verify the interaction between track sections with and without the SFO function. Refer to Coast Down Time of Carriers |
6 |
Complete installation in accordance with the EMC regulations. |
7 |
Afterwards, commission the Lexium™ MC12 multi carrier. |