Commissioning

Overview

Step

Action

1

Verify the installation. For more information, refer to Verifying the Installation.

2

Verify that a hazard and risk analysis has been performed. Refer to Hazard and Risk Analysis.

3

Carry out a functional test of the Safe Force Off (SFO) function for all segments that need the safety-related function.

4

Especially verify the correct application of the segments without the Safe Force Off (SFO) function.

5

Verify the interaction between track sections with and without the SFO function. Refer to Coast Down Time of Carriers

6

Complete installation in accordance with the EMC regulations.

7

Afterwards, commission the Lexium™ MC12 multi carrier.