Use only Schneider Electric approved devices in your application, and especially Schneider Electric pre-fabricated cables, wherever and whenever possible.
For further information, refer to Technical Data for Cables.
Use an appropriate torque indication or screwdriver for tightening connections.
Observe and implement the following points when wiring:
Use 60/75 °C (140/167 °F) copper conductors only.
Observe the minimum and maximum cross-sections of the cables necessary for the load carrying capacity of the equipment being connected.
Verify the integrity of cable shields to ensure continuity to ground.
Ensure that there is a proper, equipotential connection to ground for all interconnected equipment. The equipotential connection for the segments is implemented via the power cable.
Do not disconnect cable connection terminals when under power.
Ensure that all ground connections have sufficient surface area continuity.
Do not interchange DC+ and DC- conductors in the cable between the Lexium™ MC connection module and the Lexium™ MC12 multi carrier track.
Do not connect the DC bus directly to the power supply. Always connect the DC bus to the Lexium™ MC connection module.
Do not interchange the emergency stop circuits. This has to be observed especially when two different safety-related circuits are used.
If, for example, two parallel conductors are shown as coming from one point, you may not run just one conductor and then branch it off at a later point. If it is wired this way, induction loops (interference emitters and antennas) as well as interfering potential shifts may occur.
An incorrect wiring may result in damage of components.
CAUTION | |
---|---|