For information on the connections mentioned hereafter, refer to the Electrical Connections Overview.
To wire the controller, proceed as follows:
Step |
Action |
---|---|
1 |
Be sure that the controller is first connected to the ground (functional earth) before proceeding with other connections. |
2 |
Verify the continuity of the grounding system of your application. |
3 |
Verify that all cable shields are properly connected to the functional earth of the application. |
4 |
Verify that the memory card has been inserted. |
5 |
Eliminate the possibility of short circuits and interruptions. |
6 |
Verify that the terminals are fastened securely and the cable cross sections (gauge) are as required. |
7 |
Connect the CN9 connection of the controller to an appropriate power supply. |
8 |
Establish a Sercos connection via the CN5 and/or CN6 connections.
NOTE: If Sercos devices are assigned via the topological addresses ( = ) to the PacDrive LMC Eco, then consider the following:
|
9 |
Connect all further connections according to the requirements of your application. |
10 |
Power on the supply voltage to the controller. Result: The LMC is initialized and the LEDs show the following condition:
|
DANGER | |
---|---|
WARNING | |
---|---|
On the connection CN8, it is possible to configure the output DQ7
as watchdog output. By default, the output is configured as standard output.
WARNING | |
---|---|
For more information on safety functions, consult the standards IEC 61508:2010 and EN ISO 13849:2008.
For further information on this, see the online help of EcoStruxure Machine Expert.